Products

Data Acquisition RTUs

Selecting Hints

Compare METRAVON data acquisition RTUs for analog, digital and serial field signals. Review channel count, protocol, power, communications and remote monitoring needs.

Match the RTU to the Field Signal List

An RTU sits between field instruments and the remote monitoring system. Prepare an I/O schedule that separates analog inputs, digital inputs, pulse or rainfall inputs, relay outputs and serial devices. Then confirm polling intervals, local storage, alarm behavior, communications, power availability and the protocol expected by the control center.

Published modelDocumented standard I/OWhere to start
TG501 Compact Industrial Data Acquisition RTU2 RS232 (one debug port), 1 RS485, 3 AI and 2 DI; relay, pulse and expansion interfaces are configuration options. DC 5-35 V input. Do not count the debug port as a second instrument channel.Decentralized sites with a limited number of analog, digital and serial signals.
TG511 Multi-Channel Display Data Acquisition RTU2 RS232, 4 RS485, 8 AI, 8 DI, 2 DO, 2 relay outputs, plus rainfall and pulse inputs. DC 5-35 V input.Sites needing more channels, multiple serial networks and local display or keyboard operation.

Commission Every Channel and Failure State

  1. Compare the approved I/O list with terminal assignments, sensor ranges, engineering units and serial addresses.
  2. Apply a known value or simulator to every analog channel and operate each digital, pulse and relay point that is part of the project.
  3. Verify local records, timestamps, alarm thresholds and the values received by the remote platform.
  4. Interrupt communications and power to confirm storage, retransmission and restart behavior required by the project.

For quotation, provide the complete signal list, sensor output types, serial protocols, reporting interval, alarm and control requirements, power and enclosure conditions, communications available at site and the destination system. If the main task is connecting several PLCs or converting protocols between plant networks and a server, compare the industrial IoT gateway route as well.

Get Selection Recommendations

Please fill in the measurement media, the scale, temperature, pressure, installation and output requirements. We will provide model advice and quotations based on the field situation.